When a capital project overruns, contingency, sponsors and lenders share the bill in a set order

Grey concrete dam

In brief

  • The problem: large projects overrun.; Flyvbjerg, Holm and Buhl (2002) show that cost underestimation in large public works is systematic, not random; Bain finds that the top reason projects run late or over budget is “not making good decisions with the right people and not making them happen” (Bain).
  • The stakes: an overrun beyond the funded layers stops the lenders and can stop the project. Bain warns that when a project is off track, “it’s typically more serious than the current reporting suggests” (Bain).
  • The resolution: a set order of contingency, standby equity, standby debt, then default. In ICONIC’s worked case of a US$1bn project, a 20% overrun uses US$200m of the US$225m package. A 35% overrun leaves US$125m unfunded.

Chapter 1

How often do large projects overrun?

Bain notes that 80–90% of costs are incurred in the later phases, while the decisions that set them are taken early (Bain).

Often enough that lenders assume they will. Flyvbjerg, Holm and Buhl (2002) studied large transport projects and found costs underestimated far more often than overestimated. They concluded that the pattern cannot be explained by error alone. The gap between plan and practice starts inside the project. Accenture finds that 73–77% of leaders believe they improve cost, planning and schedule performance, while only 13% of workers say those decisions guide their daily work (Accenture).

Download the PDF

Where do overruns start?

Most of a project’s cost is fixed by decisions made before most of the money is spent. Bain notes that 80–90% of costs are incurred in the later phases, while the decisions that set them are taken early (Bain). It recommends cost and schedule baselines “grounded in reference-class data, not bottom-up estimates built by the teams delivering them” (Bain). Simplifying design can save money: on one project, reviewing 71 engineering actions saved 1–2.5% of costs (Bain).

Topics to consider at this stage

  • Is the budget’s contingency based on reference-class data for similar projects?
  • Who holds the contingency: the contractor, the sponsor or the lenders’ account?

Most of a project’s cost is fixed by decisions made before most of the money is spent.

Key number

US$125m

Unfunded at a 35% overrun. Source: ICONIC calculation.

Inside the paper

When a capital project overruns, contingency, sponsors and lenders share the bill in a set order

DOC IPFA-INS-PF-PFT-2611-IPF-068-V2

Fill out the form to read the full paper.

PDF edition

Download the full Insight

Register below. We will ask you to confirm your e-mail address and then send you a personal download link.

Chapter 2

Framework: who pays which part, and when do lenders stop?

The framework follows one project through three overruns.

The framework follows one project through three overruns. The arithmetic is ICONIC’s.

OverrunContingencyStandby equityStandby debtUnfunded
10% (US$100m)US$100m———
20% (US$200m)US$100mUS$50mUS$50m—
35% (US$350m)US$100mUS$50mUS$75mUS$125m
Exhibit 1. A US$1bn project and its overrun package. (ICONIC calculation: contingency 10% (US$100m) in the budget; standby equity US$50m; standby debt US$75m; layers used in that order)

What it means for the sponsor and the lenders. An overrun is paid by someone; the contracts decide who. Up to US$225m in this case, the package pays and the project finishes. Beyond it, the lenders usually stop funding until the gap is filled. The sponsor must then find new equity, the lenders must agree new debt, or the project defaults.

Formula 1 (ICONIC): Unfunded = max(0, Overrun − Contingency − Standby equity − Standby debt)

Topics to consider at this stage

  • Does standby equity come before or alongside standby debt?
  • What test stops the lenders’ funding: cost to complete, or a funding gap?
NumberWhy it matters
Contingency against reference-class overrunsThe first layer
Standby equity and its triggerThe sponsor’s commitment
Standby debt and its conditionsThe lenders’ commitment
Overrun at which the package runs outThe project’s breaking point
Exhibit 2. Four numbers before financial close.

An overrun is paid by someone; the contracts decide who.

Key number

US$225m

Overrun package. Source: ICONIC calculation.

Chapter 3

What’s the bottom line?

A sponsor who sizes it on reference-class data, and agrees the order and the triggers at close, knows the overrun the project can survive.

The overrun package is the part of the financing that decides whether the project finishes. A sponsor who sizes it on reference-class data, and agrees the order and the triggers at close, knows the overrun the project can survive.

For the sponsor, this leads to three steps:

  1. Size contingency on reference-class data, not the delivery team’s estimate.
  2. Agree the order and triggers for standby equity and debt at close.
  3. Compute the overrun at which the package runs out, and plan for it.

The overrun package is the part of the financing that decides whether the project finishes.

Key number

80–90%

Cost incurred in later phases. Source: Bain.

How ICONIC can help

ICONIC Project Finance Advisory works with sponsors, owners and investors on the questions this Insight raises.

  • Capital projects. Overrun packages, reference-class contingency and lender reporting. Discuss your project.
  • Project finance transactions. Completion support structuring. Pre-screen your financing.

Summary

Large projects overrun systematically (Flyvbjerg, Holm and Buhl, 2002). Most cost is set by early decisions, and baselines should rest on reference-class data (Bain). Leaders and workers see execution differently (Accenture). In ICONIC’s worked case, a US$1bn project’s US$225m package covers a 20% overrun and leaves US$125m unfunded at 35%.

Frequently asked questions

What is standby equity?

Equity the sponsor commits at close to fund overruns, drawn only if they happen.

What is reference-class forecasting?

Estimating a project’s cost and schedule from the outcomes of similar past projects, rather than from its own plan.

References

  • Accenture (n.d.) Capital projects execution gap.
  • Bain & Company (n.d.) Capital projects consulting services.
  • Bain & Company (n.d.) Large project management in oil and gas. Bain Brief.
  • Flyvbjerg, B., Holm, M.S. and Buhl, S. (2002) ‘Underestimating costs in public works projects: error or lie?’, Journal of the American Planning Association, 68(3).

This Insight is for general information only and does not constitute investment, legal or tax advice.

About this article

Authors

ICONIC Infrastructure TeamInfrastructure, ICONIC Project Finance Advisory

Approved by

Georgos S. AndrianopoulosCFO & Family Office Project Finance InvestmentProfessional EUR-ING by academic training and Chartered Financial Analyst, Georgos turned a long CFO career into international project, shipping and corporate finance. A motorsport enthusiast and car aficionado, he brings the same discipline to every transaction: precise set-up, rigorous modelling and timing at financial close, across maritime, infrastructure, oil and gas, renewables and PPPs. He tunes each transaction like a race car.Georgos S. AndrianopoulosProfessional EUR-ING by academic training and Chartered Financial Analyst, Georgos turned a long CFO career into international project, shipping and corporate finance. A motorsport enthusiast and car aficionado, he brings the same discipline to every transaction: precise set-up, rigorous modelling and timing at financial close, across maritime, infrastructure, oil and gas, renewables and PPPs. He tunes each transaction like a race car.

Related insights