Energy project financing after the subsidy: sizing debt when part of the revenue is merchant

Tidal flat at low tide below a forested headland

In brief

  • Lenders size renewable debt on the cover ratio they demand, and that ratio rises with the share of revenue sold at market prices. On one published rule, it moves from 1.30× for a fully contracted project to 2.40× for a fully merchant one; on ICONIC’s worked case, the same project then carries 46% less debt.
  • The merchant share reaches the cost of energy through the cost of capital. Better financing explained about a quarter of the fall in the cost of German onshore wind power over 18 years; in ICONIC’s worked case, moving from a fully contracted to a fully merchant capital structure raises the capital cost of each megawatt-hour by about 11%.
  • The research does not say that every unit should be contracted. A 2025 working paper finds that 80–95% contract cover can be financed with the same equity as full cover, once the value of the merchant upside and the refinancing are counted.

Chapter 1

What happens to the debt when the subsidy contract gives way to partial cover?

Renewable projects depend on project finance more than conventional plants do.

ICONIC Project Finance Advisory works on the financing side of energy projects. For more than a decade, much of the world’s wind and solar capacity was financed on long, fixed tariffs or auctioned contracts that bought the whole output at a known price. Lenders could size debt on a cash flow that depended mainly on how much the wind blew or the sun shone.

Download the PDF

That model is changing. More projects now combine a contract for part of their output, a corporate power purchase agreement (PPA) or a contract for difference, with sales at market prices for the rest. ICONIC’s Insight 010 looked at the corporate PPA from the buyer’s side. This Insight takes the lender’s side: what happens to the debt when part of the revenue has no contract behind it.

Why does the financing structure matter more for renewables?

Renewable projects depend on project finance more than conventional plants do.

  • Who uses project finance. Steffen (2018) studied German power projects from 2010 to 2015 and found that project finance matters far more for renewable projects than for fossil plants. The driver is the debt overhang of sponsors that are not utilities: developers, funds and other investors without the balance sheet to finance the plant themselves.
  • What financing does to cost. Egli, Steffen and Schmidt (2018) followed 133 German solar and wind projects over 18 years. Better financing conditions, from lower interest rates and lenders’ growing experience with the technologies, explained about 5% of the fall in the cost of solar electricity and about 24% for onshore wind.
  • Where capital is cheapest. Steffen (2020) estimated the cost of capital for renewable projects in 46 countries from 2009 to 2017. He found a consistent ranking: solar is cheapest to finance, then onshore wind, then offshore wind, and capital costs more in developing countries.

The lesson for a sponsor is that the structure of revenue and the structure of finance are linked. A change in one shows up in the other, and then in the price of the energy.

Topics to consider at this stage

  • What share of the project’s output will be contracted, for how long, and with whom?
  • Does the sponsor have the balance sheet to finance the plant itself, or does it depend on project debt?

The lesson for a sponsor is that the structure of revenue and the structure of finance are linked.

Inside the paper

Energy project financing after the subsidy: sizing debt when part of the revenue is merchant

DOC IPFA-INS-PF-PFT-2611-IPF-025-V1

Fill out the form to read the full paper.

PDF edition

Download the full Insight

Register below. We will ask you to confirm your e-mail address and then send you a personal download link.

Chapter 2

Test 1. How much debt does the merchant share cost?

Lenders size project debt by sculpting: each year’s debt service is set so that cash flow covers it by a minimum ratio.

The framework asks three questions about a project with merchant revenue:

  • how much debt does the merchant share cost;
  • what does it do to the cost of capital and the cost of energy;
  • how much contract cover is enough.

The first and third rest on the debt-sizing rule of a 2025 working paper (Gohdes, 2025). The second uses the findings of Egli, Steffen and Schmidt (2018) and the standard capital recovery formula. ICONIC’s arithmetic is labelled as such.

Lenders size project debt by sculpting: each year’s debt service is set so that cash flow covers it by a minimum ratio. Gohdes (2025) models a renewable project whose output is partly contracted and partly sold at market prices, and sets the minimum ratio as a blend of the two:

Formula 1 (Gohdes, 2025, equations A.20 and A.21)

DSCR=1.30·C+2.40·(1−C),DSt=CFADSt·1DSCR

where:

  • C is the share of output covered by the power purchase agreement (0 to 1);
  • DSCR is the minimum debt service cover ratio the lenders require;
  • DSₜ is debt service in year t;
  • CFADSₜ is the cash flow available for debt service in year t.

The 1.30 and 2.40 are the paper’s assumptions for the contracted and the merchant ratio, not market quotations. Its table of assumptions also gives 1.35 for the contracted case and gearing limits of 80% contracted and 50% merchant.

A worked case (ICONIC’s own arithmetic). A project produces CFADS of US$100m a year. Debt runs for 15 years at 6%. The debt it can carry is the present value of the debt service that Formula 1 allows.

Contracted share (C)Required DSCRDebt capacity (US$m)Share of fully contracted
100%1.30×747100%
90%1.41×68992%
80%1.52×63986%
50%1.85×52570%
0%2.40×40554%
Exhibit 1. Cover ratio and debt capacity by contracted share. (ICONIC calculation from Formula 1) Reading note: each ten points of merchant exposure add about 0.11 to the cover ratio. At 80% cover, the same cash flow carries about one-seventh less debt; fully merchant, about half less. Source: ICONIC analysis using the sizing rule of Gohdes (2025). Cash flow, rate and tenor are assumptions for illustration.
Figure 1. Debt capacity by contracted shareHorizontal bar chart of debt capacity in US dollars million by contracted share, with the cover ratio the lenders require: 100 per cent contracted at 1.30 times, 747; 90 per cent at 1.41 times, 689; 80 per cent at 1.52 times, 639; 50 per cent at 1.85 times, 525; 0 per cent at 2.40 times, 405. Debt capacity falls as the merchant share grows.100% contracted, DSCR 1.30×74790% contracted, DSCR 1.41×68980% contracted, DSCR 1.52×63950% contracted, DSCR 1.85×5250% contracted, DSCR 2.40×4050200400600800Debt capacity, US$m
Figure 1. Debt capacity by contracted share. Reading note: the values of Exhibit 1, in US$m. Source: ICONIC calculation from Formula 1.

What it means for the sponsor. The merchant share is paid for twice: once in the price risk the sponsor keeps, and once in the debt the lenders withhold. The second cost is the easier one to compute, and it should be computed before the PPA is negotiated.

Limits.

  • The rule is linear in C. Lenders may apply a different blend, or size the merchant part on a separate downside price case.
  • The worked case holds CFADS constant. A merchant project’s cash flow in the lenders’ case is usually lower than in the sponsor’s case, which widens the gap.

Topics to consider at this stage

  • What cover ratio will the lenders apply to the merchant share, and on what price case?
  • How much debt does each additional ten points of contract cover buy?

The merchant share is paid for twice: once in the price risk the sponsor keeps, and once in the debt the lenders withhold.

Fully merchant

2.40×

The cover ratio lenders require of a fully merchant project, against 1.30× fully contracted. Source: Gohdes (2025).

Chapter 3

Test 2. What does the merchant share do to the cost of energy?

Less debt means more equity, and equity costs more than debt.

Less debt means more equity, and equity costs more than debt. The weighted average cost of capital (WACC) therefore rises with the merchant share. Egli, Steffen and Schmidt (2018) show how much this matters: financing conditions explain about a quarter of the fall in the cost of onshore wind power in Germany over their period.

The capital part of the cost of energy follows from the standard capital recovery formula:

Formula 2 (standard capital recovery; ICONIC application)

k=I·CRF(w,n)8.76·κ,CRF(w,n)=w1−(1+w)−n,w=g·rd+(1−g)·re

where:

  • k is the capital cost per megawatt-hour (US$/MWh);
  • I is the investment per kilowatt (US$/kW);
  • κ is the capacity factor; 8.76 converts a kilowatt to megawatt-hours a year;
  • n is the economic life in years;
  • w is the WACC, g the gearing, r_d the cost of debt and r_e the cost of equity (tax ignored).

A worked case (ICONIC’s own arithmetic). A wind project costs US$1,000 per kW, runs at a 35% capacity factor for 25 years, and borrows at 5% against equity at 10%. Gohdes (2025) reports gearing ceilings of about 71% for a fully contracted asset and about 47% for a fully merchant one.

StructureGearingWACCCapital cost (US$/MWh)Equity per US$100 of investment
Fully contracted71%6.45%26.629
Fully merchant47%7.65%29.653
Exhibit 2. From contract cover to the capital cost of energy. (ICONIC calculation from Formula 2) Reading note: the merchant structure raises the capital cost of each megawatt-hour by about 11% and nearly doubles the equity the sponsor must commit. Source: ICONIC analysis; gearing ceilings from Gohdes (2025); other inputs are assumptions for illustration.
Figure 2. Equity per US$100 of investmentHorizontal bar chart of the equity the sponsor commits per 100 US dollars of investment: fully contracted, at 71 per cent gearing, 29; fully merchant, at 47 per cent gearing, 53. The merchant structure nearly doubles the equity.Fully contracted, gearing 71%29Fully merchant, gearing 47%530102030405060Equity per US$100 of investment, US$
Figure 2. Equity per US$100 of investment. Reading note: the last column of Exhibit 2, in US$. Source: ICONIC calculation from Formula 2.

What it means for the sponsor. For a sponsor with limited equity, the second column of the table matters as much as the fourth. Steffen (2018) shows that such sponsors are the main users of project finance. A structure that needs nearly twice the equity may simply not be available to them.

Limits.

  • Tax, operating cost and the timing of construction are ignored.
  • The cost of equity is held constant. In practice, equity investors also ask for more on a merchant project, which widens the gap.

Topics to consider at this stage

  • What WACC does each candidate contract cover imply, and what price of energy does the project then need?
  • Can the sponsor commit the equity that a lower gearing requires?

Capital cost

11%

The rise in the capital cost of each megawatt-hour, fully merchant against fully contracted. ICONIC worked case.

Chapter 4

Test 3. How much contract cover is enough?

The two views can be reconciled.

Tests 1 and 2 might suggest that every unit should be contracted. The literature does not agree. Gohdes (2025) models the whole life of a project, including the value of market sales above the contract price and the refinancing of the debt after seven years. He finds that a semi-merchant structure with 80–95% PPA cover appears viable with the same quantum of equity capital as a fully contracted one, without a material rise in the risk of technical default. Above that, more contracting adds little value for equity.

The two views can be reconciled. A static sizing, as in Exhibit 1, counts only what the merchant share costs at financial close. A full-life model also counts what it earns: market revenue above the PPA price, and a refinancing on better terms once the project has a record. The answer depends on the lenders’ price case and on whether the refinancing is likely.

A worked case (ICONIC’s own arithmetic). From Exhibit 1, moving from 100% to 90% cover costs about 8% of debt capacity at close, US$58m on the worked case. That is the amount the merchant 10% must recover over the life of the project, through prices above the PPA or a better refinancing, for the sponsor to be no worse off.

What it means for the sponsor. The right contract cover is not a rule of thumb. It is the point where the debt given up at close is earned back over the life of the project, and it can be computed for each project.

Limits.

  • Gohdes (2025) is a working paper, not peer-reviewed, and is calibrated to one market.
  • The value of merchant revenue depends on a price outlook that lenders and sponsors may not share.

Topics to consider at this stage

  • How much debt does the project give up at close for each band of merchant exposure, and what must the merchant revenue earn to recover it?
  • Is a refinancing after the first years part of the plan, and on what assumptions?

Contract cover

80–95%

The contract cover that can be financed with the same equity as full cover. Source: Gohdes (2025).

Chapter 5

Framework: what should the sponsor compute before the PPA is signed?

The three numbers belong in the PPA negotiation, not after it.

QuestionWhat to computeWhere it comes from
What does the merchant share cost in debt? (Test 1)Required DSCR and debt capacity by contracted shareLenders’ sizing rule; Formula 1
What does it cost in capital and energy? (Test 2)Gearing, WACC, equity needed and capital cost per MWhFormula 2
How much cover is enough? (Test 3)The debt given up at close against what the merchant share earns over the life, including refinancingFull-life model of the project
Exhibit 3. The merchant share test: what to compute before the contract is signed. Reading note: the three numbers belong in the PPA negotiation, not after it. Source: ICONIC analysis, drawing on Gohdes (2025), Egli, Steffen and Schmidt (2018) and Steffen (2018).

Chapter 6

What’s the bottom line?

As renewable projects move from full-output tariffs to partial contracts, the debt becomes a function of the contracted share.

As renewable projects move from full-output tariffs to partial contracts, the debt becomes a function of the contracted share. Lenders raise the cover ratio as the merchant share grows, the debt falls, the equity rises and so does the cost of each megawatt-hour. The research also shows that full cover is not always the best answer: once the merchant upside and the refinancing are counted, partial cover can be financed with the same equity.

For a sponsor, this leads to three steps:

  1. Before negotiating a PPA, compute the debt each level of contract cover supports in the lenders’ case.
  2. Translate the resulting gearing into the WACC, the equity cheque and the price of energy the project needs.
  3. Set the contract cover where the debt given up at close is earned back over the project’s life, and test that against the lenders’ price case.

The contract cover is therefore a financing decision, to be computed before the PPA is signed.

How ICONIC can help

ICONIC works on renewable financing from the lenders’ side, before the revenue contracts are fixed.

  • Project finance transactions. Debt sized and raised on the revenue structure chosen, with the merchant share placed where lenders will accept it. Discuss a mandate.
  • Financial modelling. A model that shows debt, equity and the cost of energy for each level of contract cover, and over the project’s whole life. Test your contract cover.
  • Equity. Equity partners for projects whose structure needs more equity than the sponsor alone can commit. Discuss your equity.

Summary

Renewable projects depend on project finance, especially when their sponsors lack the balance sheet to fund them (Steffen, 2018), and better financing explains a large part of the fall in their cost (Egli, Steffen and Schmidt, 2018). As full-output tariffs give way to partial contracts, lenders blend their cover ratio between a contracted and a merchant level. On the rule of Gohdes (2025), the ratio moves from 1.30× to 2.40× as cover falls from 100% to zero; on ICONIC’s worked case, the same cash flow then carries 46% less debt, the sponsor commits nearly twice the equity and the capital cost of energy rises by about 11%. Gohdes (2025) also finds that 80–95% cover can be financed with the same equity as full cover once the merchant upside and refinancing are counted. The contract cover is therefore a financing decision, to be computed before the PPA is signed.

Frequently asked questions

Is a fully contracted project always cheaper to finance?

At financial close, yes: it carries more debt at a lower cover ratio. Over the project’s life, not necessarily. The merchant share can earn more than the contract price and support a better refinancing, and one study finds that 80–95% cover can be financed with the same equity as full cover.

Why does the cost of energy depend on the contract cover?

Because the contract cover sets the gearing, and the gearing sets the weighted cost of capital. For capital-intensive plants such as wind and solar, the cost of capital is a large part of the cost of each megawatt-hour.

Do lenders accept merchant revenue at all?

Many do, at a higher cover ratio, on a conservative price case and often with a shorter tenor or a cash sweep. The terms vary by market and by lender, which is why they should be tested before the revenue contracts are fixed.

References

This Insight is for general information only and does not constitute investment, legal or tax advice. Figures from public sources are as reported at the dates shown.

About this article

Authors

ICONIC Energy TeamEnergy, ICONIC Project Finance AdvisoryPower bought from a plant not yet built is a promise in steel and cable. We test every link between the panels and the buyer before you sign: the PPA, the grid, curtailment and the financing.ICONIC Energy TeamPower bought from a plant not yet built is a promise in steel and cable. We test every link between the panels and the buyer before you sign: the PPA, the grid, curtailment and the financing.

Approved by

Georgos S. AndrianopoulosCFO & Family Office Project Finance InvestmentProfessional EUR-ING by academic training and Chartered Financial Analyst, Georgos turned a long CFO career into international project, shipping and corporate finance. A motorsport enthusiast and car aficionado, he brings the same discipline to every transaction: precise set-up, rigorous modelling and timing at financial close, across maritime, infrastructure, oil and gas, renewables and PPPs. He tunes each transaction like a race car.Georgos S. AndrianopoulosProfessional EUR-ING by academic training and Chartered Financial Analyst, Georgos turned a long CFO career into international project, shipping and corporate finance. A motorsport enthusiast and car aficionado, he brings the same discipline to every transaction: precise set-up, rigorous modelling and timing at financial close, across maritime, infrastructure, oil and gas, renewables and PPPs. He tunes each transaction like a race car.