Project finance advisory: how risk allocation in the contracts reaches the price of debt

A tied rope, in black and white

In brief

  • A project company has no history and no other business. Its lenders lend against the contracts around it, and the evidence from more than 2,000 loan tranches shows that the contracts move the price: a project without a construction contract paid about 32 basis points more, all else equal.
  • Contracts also set how much debt a project carries. In the same evidence, supply and operating contracts went with higher leverage. Spread and leverage are set together, so a contract can be paid for in price or in debt.
  • The same cover ratio can hide very different risk. In ICONIC’s worked case, a project with a 1.30× ratio has about an 18% yearly chance of falling short of debt service if its cash flow is volatile, and about 0.5% if contracts have taken most of the volatility out.

Chapter 1

What do lenders lend against when the borrower has no history?

Lenders read that set of contracts as their security.

ICONIC Project Finance Advisory works on the financing side of capital projects. In project finance, the borrower is a company created for one asset. It has no track record, no other business and no balance sheet beyond the asset itself. What it does have is a set of contracts: for building the asset, supplying its inputs, operating it and selling its output, with the sponsors’ support around them.

Download the PDF

Lenders read that set of contracts as their security. Each contract moves a risk from the project company to a counterparty: construction risk to the contractor, input risk to the supplier, market risk to the buyer, operating risk to the operator. Whatever is not moved stays in the project, and the lenders price it.

This is where the adviser earns its place. A project finance adviser does not change the asset. It changes the allocation of risk among the contracts, and through that the price and the amount of debt.

What does the evidence say about contracts and loans?

The research on how lenders treat these contracts is consistent.

  • Project finance loans are different. Kleimeier and Megginson (2000) compared 4,956 project finance loans, worth about US$634bn, with other syndicated credits. Project finance loans had longer maturities, more third-party guarantees and lower spreads than comparable loans.
  • Contracts move both price and leverage. Corielli, Gatti and Steffanoni (2010) studied project finance loans from 1998 to 2003 and found that lenders use the network of non-financial contracts to control risk. Their results are the subject of Test 1.
  • Lenders price the residual. Dailami and Hauswald (2007) found that the bondholders of an LNG project priced the risks its contracts left open, and largely ignored the risk its sponsor had guaranteed. ICONIC’s Insight on LNG commercial structuring takes up that case.

Topics to consider at this stage

  • Has anyone listed, contract by contract, which risks leave the project company and which stay?
  • Are the contracts being negotiated with the lenders’ reading in mind, or will they be defended to the lenders afterwards?

Whatever is not moved stays in the project, and the lenders price it.

Inside the paper

Project finance advisory: how risk allocation in the contracts reaches the price of debt

DOC IPFA-INS-PF-PFT-2611-IPF-026-V1

Fill out the form to read the full paper.

PDF edition

Download the full Insight

Register below. We will ask you to confirm your e-mail address and then send you a personal download link.

Chapter 2

Test 1. Which contracts move the price of debt?

Construction risk is the risk lenders price most directly, because it falls before the project has any cash flow.

The framework asks three questions about a project’s contracts:

  • which contracts move the price of debt;
  • which move the amount of debt;
  • how much cover ratio a contract is worth.

The first two rest on the published evidence of Corielli, Gatti and Steffanoni. The third uses a standard credit model applied by ICONIC.

Corielli, Gatti and Steffanoni estimate how the presence of each main contract, and whether a sponsor is its counterparty, affects the spread of a project finance loan. Because the spread and the leverage are decided together, they estimate two equations jointly. In ICONIC’s notation of the system the authors describe:

Formula 1 (after Corielli, Gatti and Steffanoni, 2010; ICONIC notation)

si=a+γ(D/E)i+∑kβkNok,i+∑kδkSponsork,i+controls+ui(D/E)i=b+θsi+∑kφkNok,i+∑kψkSponsork,i+controls+vi

where:

  • sᵢ is the spread of loan tranche i over its benchmark, in basis points;
  • (D/E)ᵢ is the project’s debt-to-equity ratio;
  • Noₖ,ᵢ is 1 when contract k is absent: construction, engineering-procurement-construction (EPC), offtake, supply, equipment supply, or operation and maintenance;
  • Sponsorₖ,ᵢ is 1 when a sponsor is the counterparty to contract k;
  • the controls are country rating, sector, refinancing, currency risk, tranche size and maturity.

The authors estimate the system by two-stage least squares on 2,198 loan tranches of 1,145 projects, worth about US$428bn, closed between January 1998 and May 2003.

Contract absentEffect on spread (bp)Statistically significant?
Construction agreement+32.1Yes, at 1%
Equipment supply agreement+12.5No
Supply agreement+9.6No
Offtake agreement−0.9No
EPC agreement−9.2No
Operation and maintenance agreement−1.4No
Exhibit 1. What the absence of a contract did to the spread. (complete model; selected results) Reading note: of the six contracts, only the construction agreement moved the spread with statistical confidence. The others did not, on their own; their effect shows up in leverage (Test 2). Source: Corielli, Gatti and Steffanoni, conference version of the 2010 paper (EFMA, 2008), Table 7.
Figure 1. Effect on the spread of each absent contractHorizontal bar chart of the effect on a loan’s spread, in basis points, when each contract is absent: construction agreement plus 32.1, the only effect significant at 1 per cent; equipment supply agreement plus 12.5; supply agreement plus 9.6; offtake agreement minus 0.9; operation and maintenance agreement minus 1.4; EPC agreement minus 9.2.Construction agreement+32.1, significant at 1%Equipment supply agreement+12.5Supply agreement+9.6Offtake agreement−0.9Operation and maintenance agreement−1.4EPC agreement−9.2-10010203040Effect on the spread when the contract is absent, basis points
Figure 1. Effect on the spread of each absent contract. Reading note: the values of Exhibit 1, in basis points; only the black bar is statistically significant. Source: Corielli, Gatti and Steffanoni (EFMA, 2008), Table 7.

What it means for the sponsor. Construction risk is the risk lenders price most directly, because it falls before the project has any cash flow. A project that leaves construction risk with itself, rather than with a contractor under a construction agreement, should expect to pay for it in the spread.

Limits.

  • The figures come from the conference version of the paper; the published version may differ.
  • The data end in 2003. Markets, lenders and contract forms have changed since.
  • A dummy for a contract’s presence says nothing about its terms. A weak construction contract may be worth less than none at all to a lender who reads it.

Topics to consider at this stage

  • Who carries construction risk, under what contract, and with what security behind it?
  • Which contracts are the lenders likely to price, and which will they treat as given?

Without a construction agreement

32 bp

The extra spread paid, all else equal. Source: Corielli, Gatti and Steffanoni.

Chapter 3

Test 2. Which contracts move the amount of debt?

Contracts that steady the operating cash flow let the project carry more debt.

The second equation of Formula 1 shows the other channel. In the same sample (1,278 projects, 3,455 tranches, about US$546bn), the authors find that the absence of a supply agreement went with about one point less of debt-to-equity, and the absence of an operation and maintenance agreement with about half a point less. Contracts that steady the operating cash flow let the project carry more debt.

The authors also tested whether contracts signed by sponsors count for more than contracts with third parties. The support was weak. For leverage, the sign ran the other way: projects carried more debt when third parties, not sponsors, signed the contracts. The authors note that this contradicts what arrangers told them in interviews.

What it means for the sponsor. A contract can be paid for in two currencies: a lower spread or a higher debt. Because the two are set together, a negotiation that looks only at the spread can leave debt on the table, and one that looks only at gearing can overpay for it. The adviser’s task is to read both.

Limits.

  • The leverage results are reported in the paper’s text; the full table was not visible in the version opened.
  • The sponsor result is weak and runs against market practice. It should be read as an open question, not a rule.

Topics to consider at this stage

  • Which contracts steady the operating cash flow, and has their effect on gearing been priced into the negotiation?
  • Is a sponsor the counterparty to a key contract, and does that strengthen the credit or only appear to?

A contract can be paid for in two currencies: a lower spread or a higher debt.

Without a supply agreement

1 point

Less debt-to-equity. Source: Corielli, Gatti and Steffanoni.

Chapter 4

Test 3. How much cover ratio is a contract worth?

The cover ratio is a price for volatility.

Lenders set a minimum debt service cover ratio (DSCR), but a ratio is an average. What matters is how often cash flow falls below debt service in a bad year. That depends on the volatility the contracts leave in the cash flow. Gatti, Rigamonti, Saita and Senati (2007) proposed Monte Carlo simulation for lenders to measure that risk. A closed-form version gives the same intuition.

Formula 2 (lognormal cash flow; ICONIC application of a standard credit model)

Pr(CFADS<DS)=Φ(−lnDSCR―+12σe2σe),σe=(1−h)σ

where:

  • CFADS is the cash flow available for debt service in a year, and DS the debt service;
  • DSCR̄ is the expected cover ratio, CFADS over DS;
  • σ is the volatility of the logarithm of cash flow without contracts;
  • h is the share of that volatility moved to counterparties by contracts (0 to 1);
  • Φ is the standard normal distribution function.
Effective volatility σₑDSCR 1.20×DSCR 1.30×DSCR 1.40×
0.2527.3%17.8%11.1%
0.2020.9%11.3%5.7%
0.1512.7%4.7%1.5%
0.103.8%0.5%under 0.1%
Exhibit 2. Yearly probability that cash flow falls short of debt service. (ICONIC calculation from Formula 2) Reading note: moving from a volatility of 0.25 to 0.10 cuts the yearly chance of a shortfall at 1.30× from about one in six to about one in two hundred. A contract that takes volatility out is worth more than several tenths of cover ratio. Source: ICONIC analysis. Volatilities are assumptions for illustration. A shortfall here means a draw on reserves or a lock-up, not a default.
Figure 2. Shortfall probability at a 1.30× cover ratioHorizontal bar chart of the yearly probability that cash flow falls short of debt service at a 1.30 times cover ratio, by effective volatility: 0.25, 17.8 per cent; 0.20, 11.3 per cent; 0.15, 4.7 per cent; 0.10, 0.5 per cent.Volatility 0.2517.8%Volatility 0.2011.3%Volatility 0.154.7%Volatility 0.100.5%05101520Yearly probability of a shortfall at 1.30×, %
Figure 2. Shortfall probability at a 1.30× cover ratio. Reading note: the 1.30× column of Exhibit 2. Source: ICONIC calculation from Formula 2.

A worked case (ICONIC’s own illustration). A project with σ = 0.25 and no contracts has the same 17.8% shortfall chance at 1.30× as the table shows. To bring that chance below 5% without contracts, its lenders would need a ratio well above 1.40×, and so less debt. Contracts that remove 40% of the volatility (h = 0.4, σₑ = 0.15) bring the chance to 4.7% at 1.30×, with the debt unchanged.

What it means for the sponsor. The cover ratio is a price for volatility. Contracts that move volatility to counterparties can buy a lower ratio, or the same ratio with a smaller chance of lock-up. Either is worth computing before a contract is signed.

Limits.

  • One period and a lognormal cash flow are simplifications; real projects have correlated years and fatter tails.
  • The model assumes the counterparties perform. A contract with a weak counterparty moves volatility only on paper.

Topics to consider at this stage

  • How volatile is the project’s cash flow before and after its contracts, and has anyone measured it?
  • Would the lenders accept a lower cover ratio if more of the volatility were moved to creditworthy counterparties?

At 1.30×

17.8%

The yearly chance of a shortfall when cash-flow volatility is 0.25. ICONIC worked case.

Chapter 5

Framework: what can each contract buy?

Each row is a negotiation in which the sponsor can take its gain in spread, in debt or in cover ratio.

ContractRisk it movesWhat the evidence says it buysWhat to check
ConstructionCost and delay before cash flow startsA lower spread (Test 1)The contractor’s security and the damages regime
SupplyInput volume and priceHigher leverage (Test 2)The supplier’s credit and the term against the debt
Operation and maintenancePerformance and operating costHigher leverage (Test 2)Performance guarantees and the operator’s record
OfftakePrice and volume of outputLower volatility, so a lower cover ratio (Test 3)The buyer’s credit; how long the contract runs against the debt
Exhibit 3. The risk allocation test: what each contract can buy, and how to check it. Reading note: each row is a negotiation in which the sponsor can take its gain in spread, in debt or in cover ratio. The adviser’s job is to know which. Source: ICONIC analysis, drawing on Corielli, Gatti and Steffanoni (2010) and Formula 2.

Chapter 6

What’s the bottom line?

Lenders to a project company lend against its contracts.

Lenders to a project company lend against its contracts. The evidence shows that the construction contract moves the spread, that supply and operating contracts move the debt, and that any contract that takes volatility out of the cash flow is worth cover ratio. The allocation of risk among the contracts therefore reaches the price and the amount of debt directly, and it is set long before the term sheet.

For a sponsor, this leads to three steps:

  1. List each risk, the contract that moves it and the party that receives it, before the contracts are signed.
  2. For each contract, decide whether the gain is to be taken in spread, in debt or in cover ratio, and negotiate for it.
  3. Measure the cash-flow volatility the contracts leave, and put it to the lenders with the request for a cover ratio.

Risk allocation in the contracts is therefore the adviser’s main lever on the price and the amount of debt.

How ICONIC can help

ICONIC reads a project’s contracts as the lenders will, before they are signed.

  • Project finance transactions. A financing structure in which each contract’s risk allocation is used to win price, debt or cover. Discuss a mandate.
  • Due diligence. A review of the contract set and of the risks it leaves with the project company. Ask for a contract review.
  • Financial modelling. A model of cash-flow volatility and shortfall risk with and without each contract. Test your cover ratio.

Summary

A project company borrows against its contracts. Kleimeier and Megginson (2000) show that project finance loans are longer and cheaper than comparable credits. Corielli, Gatti and Steffanoni (2010) show that lenders use the contract network to control risk: in their data, a project without a construction agreement paid about 32 basis points more, while supply and operating contracts went with higher leverage. Dailami and Hauswald (2007) show that lenders price the risks the contracts leave open. ICONIC’s own model shows that at a 1.30× cover ratio, cutting cash-flow volatility from 0.25 to 0.10 reduces the yearly chance of a shortfall from about 18% to about 0.5%. Risk allocation in the contracts is therefore the adviser’s main lever on the price and the amount of debt.

Frequently asked questions

Does every contract lower the price of debt?

No. In the evidence, only the construction agreement lowered the spread with statistical confidence. Supply and operating contracts showed up in higher leverage instead.

Is a contract with a sponsor worth more to lenders than one with a third party?

The evidence is weak and mixed. Arrangers often say so, but the data studied by Corielli, Gatti and Steffanoni showed more leverage when third parties signed. The answer depends on the sponsor’s credit and on what the contract says.

Why not simply ask for a higher cover ratio?

Because a higher ratio means less debt. Moving volatility to creditworthy counterparties can give the lenders the same protection with more debt, which is usually cheaper for the sponsor.

References

  • Corielli, F., Gatti, S. and Steffanoni, A. (2008) ‘Risk shifting through nonfinancial contracts: effects on loan spreads and capital structure of project finance deals’. Paper presented at the European Financial Management Association annual meeting, Athens. Available at: https://www.efmaefm.org/0EFMAMEETINGS/EFMA%20ANNUAL%20MEETINGS/2008-Athens/papers/Gatti.pdf
  • Corielli, F., Gatti, S. and Steffanoni, A. (2010) ‘Risk shifting through nonfinancial contracts: effects on loan spreads and capital structure of project finance deals’, Journal of Money, Credit and Banking, 42(7), pp. 1295–1320. doi:10.1111/j.1538-4616.2010.00342.x
  • Dailami, M. and Hauswald, R. (2007) ‘Credit-spread determinants and interlocking contracts: a study of the Ras Gas project’, Journal of Financial Economics, 86(1), pp. 248–278. doi:10.1016/j.jfineco.2007.03.001
  • Gatti, S., Rigamonti, A., Saita, F. and Senati, M. (2007) ‘Measuring value-at-risk in project finance transactions’, European Financial Management, 13(1), pp. 135–158. doi:10.1111/j.1468-036X.2006.00288.x
  • Kleimeier, S. and Megginson, W.L. (2000) ‘Are project finance loans different from other syndicated credits?’, Journal of Applied Corporate Finance, 13(1), pp. 75–87. doi:10.1111/j.1745-6622.2000.tb00043.x

This Insight is for general information only and does not constitute investment, legal or tax advice. Figures from public sources are as reported at the dates shown.

About this article

Authors

ICONIC Infrastructure TeamInfrastructure, ICONIC Project Finance Advisory

Approved by

Georgos S. AndrianopoulosCFO & Family Office Project Finance InvestmentProfessional EUR-ING by academic training and Chartered Financial Analyst, Georgos turned a long CFO career into international project, shipping and corporate finance. A motorsport enthusiast and car aficionado, he brings the same discipline to every transaction: precise set-up, rigorous modelling and timing at financial close, across maritime, infrastructure, oil and gas, renewables and PPPs. He tunes each transaction like a race car.Georgos S. AndrianopoulosProfessional EUR-ING by academic training and Chartered Financial Analyst, Georgos turned a long CFO career into international project, shipping and corporate finance. A motorsport enthusiast and car aficionado, he brings the same discipline to every transaction: precise set-up, rigorous modelling and timing at financial close, across maritime, infrastructure, oil and gas, renewables and PPPs. He tunes each transaction like a race car.