When should a project reprice its debt, and who keeps the gain?

Greyscale concrete building

In brief

  • Before: project loans are priced at financial close for construction and ramp-up risk. Kleimeier and Megginson (2000) show that project finance loans differ from other syndicated loans in maturity, syndication and pricing. Sorge and Gadanecz (2008) show that project spreads behave differently over time.
  • After: an operating project has a record, and its risk is lower. Refinancings follow, from wastewater PPPs (WFW, 2023) to shipping portfolios (WFW, 2022).
  • The bridge: reprice when the saving exceeds the cost, and share it as the contract requires. In ICONIC’s worked case, refinancing a PPP loan of 800 in year 4 at 80 bp lower gains about 67 after break costs, about 34 of it for the public side at a 50:50 split.

Chapter 1

Why do projects refinance after construction?

In a PPP, the public side shares a gain it helped create.

Construction debt is priced for risks the operating project no longer has. Once a project has operated, the lender’s view changes. Output is known, costs are known, and the completion risk that set the margin has gone. Refinancing replaces the construction-era margin with one priced for operation:

Download the PDF

  • WFW advised Abanca on refinancing seven wastewater treatment plants held under a PPP concession (WFW, 2023);
  • WFW also advised HCOB on a US$95m facility to refinance seven vessels (WFW, 2022).

Who has a claim on the gain?

In a PPP, the public side shares a gain it helped create. Its contract usually entitles it to a share of any refinancing gain, because the gain comes partly from the low risk of its own payments. When the project is weak rather than strong, refinancing becomes restructuring. In Bourbon Maritime’s case, creditors cut debt from about €2.7bn to about €1.065bn. They converted €228m into bonds redeemable in shares and injected €150m of new senior money (WFW, 2021).

Topics to consider at this stage

  • Does the concession require the public side’s consent to refinance, and share the gain?
  • What does it cost to leave the existing loan: swap breakage, fees, consents?

Construction debt is priced for risks the operating project no longer has.

Key number

€2.7bn → €1.065bn

Bourbon debt. Source: WFW.

Inside the paper

When should a project reprice its debt, and who keeps the gain?

DOC IPFA-INS-PF-PFT-2611-IPF-063-V2

Fill out the form to read the full paper.

PDF edition

Download the full Insight

Register below. We will ask you to confirm your e-mail address and then send you a personal download link.

Chapter 2

Framework: when does refinancing pay, and how is the gain split?

The framework prices the gain and its split.

The framework prices the gain and its split. The arithmetic is ICONIC’s.

Formula 1 (ICONIC): Net gain = Loan × Margin saving × annuity factor − Break costs and fees

Formula 2 (ICONIC): Public share = Net gain × agreed share

ItemAmount
Gross saving, present valueabout 77
Break costs and feesabout 10
Net gainabout 67
Public side’s share at 50%about 34
Exhibit 1. A PPP loan refinanced in year 4. (ICONIC calculation: loan 800 with 22 years left; margin 80 bp lower; break costs and fees 1.2% of the loan; discount rate 6%; 50:50 gain share)

What it means for the owner and the public side. A refinancing pays when the margin saving, over the remaining life, exceeds the cost of leaving the loan by enough to share. The public side’s share is a payment it can take in cash or as lower unitary payments.

Topics to consider at this stage

  • Is the gain computed on a pre-agreed method, or negotiated each time?
  • Does the refinancing add debt or extend tenor, and so add risk the public side carries?
NumberWhy it matters
Margin saving over the remaining lifeThe gross gain
Break costs, fees and consentsThe cost of leaving
Gain-share methodWho keeps what
Change in debt and tenorWhether risk rises with the gain
Exhibit 2. Four numbers before a project refinancing.

A refinancing pays when the margin saving, over the remaining life, exceeds the cost of leaving the loan by enough to share.

Key number

about 67 / about 34

Net gain / public share. Source: ICONIC calculation.

Chapter 3

What’s the bottom line?

The owner who computes the net gain, and the public side’s share, before approaching lenders negotiates from the number, not towards it.

A project refinances when the saving exceeds the cost, and shares what the contract says it must. The owner who computes the net gain, and the public side’s share, before approaching lenders negotiates from the number, not towards it.

For the owner, this leads to three steps:

  1. Price the margin saving over the remaining life.
  2. Price the cost of leaving the loan on the day.
  3. Agree the gain-share method with the public side before going to market.

A project refinances when the saving exceeds the cost, and shares what the contract says it must.

Key number

US$95m

HCOB refinancing. Source: WFW.

How ICONIC can help

ICONIC Project Finance Advisory works with sponsors, owners and investors on the questions this Insight raises.

  • Refinancing and restructuring. Refinancing gain analysis and execution. Discuss your project.
  • PPP. Gain-share negotiation with the public side. Pre-screen your refinancing.

Summary

Project loans are priced at close for construction risk (Kleimeier and Megginson, 2000; Sorge and Gadanecz, 2008). Operating projects refinance, from wastewater PPPs to vessel portfolios (WFW, 2022; 2023), and weak ones restructure, as Bourbon’s cut from about €2.7bn to €1.065bn shows (WFW, 2021). In ICONIC’s worked case, a PPP loan of 800 refinanced at 80 bp lower gains about 67, about 34 of it for the public side.

Frequently asked questions

What is a refinancing gain?

The present value of the lower cost of debt after a refinancing, net of the costs of making it.

Why should the public side share it?

Because the gain comes partly from the low risk of the public side’s own payments, and PPP contracts usually say so.

References

  • Kleimeier, S. and Megginson, W.L. (2000) ‘Are project finance loans different from other syndicated credits?’, Journal of Applied Corporate Finance, 13(1).
  • Sorge, M. and Gadanecz, B. (2008) ‘The term structure of credit spreads in project finance’, International Journal of Finance and Economics, 13(1), pp. 68–81.
  • WFW (2021) WFW advises group of core creditors on Bourbon Maritime debt restructuring.
  • WFW (2022) WFW advises HCOB on US$95m seven vessel refinancing.
  • WFW (2023) WFW advises Abanca on wastewater treatment infrastructure project refinancing.

This Insight is for general information only and does not constitute investment, legal or tax advice.

About this article

Authors

ICONIC Infrastructure TeamInfrastructure, ICONIC Project Finance Advisory

Approved by

Georgos S. AndrianopoulosCFO & Family Office Project Finance InvestmentProfessional EUR-ING by academic training and Chartered Financial Analyst, Georgos turned a long CFO career into international project, shipping and corporate finance. A motorsport enthusiast and car aficionado, he brings the same discipline to every transaction: precise set-up, rigorous modelling and timing at financial close, across maritime, infrastructure, oil and gas, renewables and PPPs. He tunes each transaction like a race car.Georgos S. AndrianopoulosProfessional EUR-ING by academic training and Chartered Financial Analyst, Georgos turned a long CFO career into international project, shipping and corporate finance. A motorsport enthusiast and car aficionado, he brings the same discipline to every transaction: precise set-up, rigorous modelling and timing at financial close, across maritime, infrastructure, oil and gas, renewables and PPPs. He tunes each transaction like a race car.