ICONIC Project Finance Advisory logo ICONIC
Project Finance Advisory

What do lenders need before the first commercial floating wind farm?

Offshore turbines in a foggy sea

In brief

  • And: floating wind opens deep water. Norway’s Utsira Nord, three areas of 500 MW each with an average depth of 265 metres, suits floating turbines (Wikborg Rein, 2023).
  • But: floating wind has no long operating record at commercial scale, so lenders price technology risk with a higher cover ratio and a smaller loan. Myhr et al. (2014) show how cost depends on the floating concept and its life-cycle assumptions.
  • Therefore: warranties, export credit agency (ECA) cover and grants stand in for the record. In ICONIC’s worked case of a 500 MW farm, an extended warranty adds about 7% to the debt, and a 30% ECA-covered tranche on top adds about 15% in all.

Chapter 1

Why does floating wind need a different financing?

A lender prices what it has seen fail; floating wind has not run long enough to fail.

Because its risks are new. Fixed-bottom offshore wind has a long operating history; floating platforms, moorings and dynamic cables have less. The Norwegian state allocates Utsira Nord on qualitative criteria designed “to develop expertise and technology”, not on price alone (Wikborg Rein, 2023). Technology developers share intellectual property and risk under development agreements whose terms vary widely (Wikborg Rein, 2021). Myhr et al. (2014) estimate the levelised cost of floating concepts and show how sensitive it is to their design and life-cycle assumptions.

Download the PDF

What do lenders do without an operating record?

A lender prices what it has seen fail; floating wind has not run long enough to fail. It raises the cover ratio, shortens the tenor or lends less, unless something else carries the technology risk:

  • a manufacturer’s warranty;
  • a guarantee;
  • a grant.

Topics to consider at this stage

  • Which components have no commercial operating record?
  • Who will warrant them, for how long, and with what balance sheet?

A lender prices what it has seen fail; floating wind has not run long enough to fail.

Key number

+7% / +15%

Debt added by warranty / warranty and ECA. Source: ICONIC calculation.

Inside the paper

What do lenders need before the first commercial floating wind farm?

DOC IPFA-INS-PF-PFT-2611-IPF-060-V2

Fill out the form to read the full paper.

PDF edition

Download the full Insight

Register below. We will ask you to confirm your e-mail address and then send you a personal download link.

Chapter 2

Framework: what substitutes for a track record?

The framework sizes the debt with and without substitutes for a track record.

The framework sizes the debt with and without substitutes for a track record. The arithmetic and assumed terms are ICONIC’s.

StructureDSCRDebt
No substitute1.45×about US$832m
Extended manufacturer’s warranty1.35×about US$894m
Warranty and 30% ECA-covered tranche1.30×about US$961m
Exhibit 1. A 500 MW floating wind farm. (ICONIC calculation: CFADS US$120m a year; 18 years; interest 7%; ECA-covered tranche at 5.5%; cover ratios are ICONIC assumptions)

What it means for the sponsor. Until there is an operating record, a warranty or a guarantee stands in for it. Each lowers the cover ratio the lender needs, and the ECA tranche also lowers the rate on part of the debt. ECA cover typically covers 70–100% of principal and interest, and comes with the agency’s own conditions (Norton Rose Fulbright, 2026).

Topics to consider at this stage

  • What does the warranty cover: availability, power curve, serial defects?
  • Does the project’s supply chain qualify for ECA support?
NumberWhy it matters
Debt with no substituteThe lender’s starting point
Debt with the warrantyWhat the warranty is worth
Debt with ECA coverWhat the agency is worth
Warrantor’s balance sheetWhether the warranty is real
Exhibit 2. Four numbers before financing a first commercial floating farm.

Until there is an operating record, a warranty or a guarantee stands in for it.

Key number

265 m

Average depth, Utsira Nord. Source: Wikborg Rein.

Chapter 3

What’s the bottom line?

A sponsor who prices each substitute in debt, not only in cost, knows which to buy.

The first commercial floating wind farm is financed on borrowed track records: the manufacturer’s, the agency’s and the state’s. A sponsor who prices each substitute in debt, not only in cost, knows which to buy.

For the sponsor, this leads to three steps:

  1. Size the debt the project supports with no substitute.
  2. Price each warranty and guarantee by the debt it adds.
  3. Combine them where the debt added exceeds their cost.

The first commercial floating wind farm is financed on borrowed track records: the manufacturer’s, the agency’s and the state’s.

Key number

3 × 500 MW

Utsira Nord areas. Source: Wikborg Rein.

How ICONIC can help

ICONIC Project Finance Advisory works with sponsors, owners and investors on the questions this Insight raises.

  • Renewable energy. Technology-risk structuring for floating wind. Discuss your project.
  • Project finance transactions. ECA and lender approach. Pre-screen your financing.

Summary

Utsira Nord’s deep water suits floating turbines and is allocated on qualitative criteria (Wikborg Rein, 2023). Costs depend on the concept (Myhr et al., 2014), and lenders without an operating record price technology risk. In ICONIC’s worked case, an extended warranty adds about 7% to a 500 MW farm’s debt, and a 30% ECA-covered tranche brings the gain to about 15%.

Frequently asked questions

What is floating offshore wind?

Wind turbines mounted on floating platforms anchored to the seabed, used where water is too deep for fixed foundations.

Why does a warranty add debt?

Because it moves part of the technology risk to the manufacturer, so the lender needs less cover from the project itself.

References

  • Myhr, A., Bjerkseter, C., Ågotnes, A. and Nygaard, T.A. (2014) ‘Levelised cost of energy for offshore floating wind turbines in a life cycle perspective’, Renewable Energy, 66.
  • Norton Rose Fulbright (2026) Export credit agency financing: ten key questions answered. July 2026.
  • Wikborg Rein (2021) Floating offshore wind: how to structure technology development.
  • Wikborg Rein (2023) Launch of offshore wind tenders for Sørlige Nordsjø II and Utsira Nord.

This Insight is for general information only and does not constitute investment, legal or tax advice.

About this article

Authors

ICONIC Energy TeamEnergy, ICONIC Project Finance AdvisoryPower bought from a plant not yet built is a promise in steel and cable. We test every link between the panels and the buyer before you sign: the PPA, the grid, curtailment and the financing.ICONIC Energy TeamPower bought from a plant not yet built is a promise in steel and cable. We test every link between the panels and the buyer before you sign: the PPA, the grid, curtailment and the financing.

Approved by

Georgos S. AndrianopoulosCFO & Family Office Project Finance InvestmentProfessional EUR-ING by academic training and Chartered Financial Analyst, Georgos turned a long CFO career into international project, shipping and corporate finance. A motorsport enthusiast and car aficionado, he brings the same discipline to every transaction: precise set-up, rigorous modelling and timing at financial close, across maritime, infrastructure, oil and gas, renewables and PPPs. He tunes each transaction like a race car.Georgos S. AndrianopoulosProfessional EUR-ING by academic training and Chartered Financial Analyst, Georgos turned a long CFO career into international project, shipping and corporate finance. A motorsport enthusiast and car aficionado, he brings the same discipline to every transaction: precise set-up, rigorous modelling and timing at financial close, across maritime, infrastructure, oil and gas, renewables and PPPs. He tunes each transaction like a race car.

Related insights