Chapter 1
What must a data centre have before the first drawdown?
In power, equipment and labour:
Site control, a path to power and a credible budget. Wikborg Rein describes option agreements as “one of the key tools” for securing land in Norway. They let developers advance zoning and grid applications while deferring the purchase (Wikborg Rein, 2026). Under Statnett’s revised maturity framework, an applicant must show binding and exclusive access to the land (Wikborg Rein, 2026). The German TSOs’ proposed scoring rates projects on land and permits, technical readiness, developer capability and system value (Norton Rose Fulbright, 2026).
Where do data centre builds slip?
In power, equipment and labour:
- Bain reports equipment lead times of 8–24 months and utility connection delays of up to five years. Four actions can cut build times by up to a year (Bain, 2025).
- Turner & Townsend’s index of over 500 projects in 62 markets finds that demand for AI capacity has outpaced the supply of powered land and skilled labour (Turner & Townsend, 2026).
- It also finds a 7–10% US construction cost premium for AI data centres over traditional ones (Turner & Townsend, 2025).
- Flyvbjerg, Holm and Buhl (2002) show that cost underestimation is systematic in large projects.
Topics to consider at this stage
- Which milestones are proven today, and which depend on third parties?
- Which long-lead items must be ordered before the loan closes?
Site control, a path to power and a credible budget.
Key number
5.5%
Inside the paper
Lenders fund a data centre one milestone at a time, from site control to energisation
DOC IPFA-INS-PF-PFT-2611-IPF-050-V2
Fill out the form to read the full paper.
Download the PDFPDF edition
Download the full Insight
Register below. We will ask you to confirm your e-mail address and then send you a personal download link.
Chapter 2
Framework: what does the lender test at each milestone?
The framework follows one campus through six milestones.
The framework follows one campus through six milestones. The arithmetic is ICONIC’s.
| Milestone | What the lender tests | Share of spend | Cost of a three-month slip |
|---|---|---|---|
| 1. Site control | Option or title; mortgage path | 3% | about US$0.2m |
| 2. Zoning | Permission for data centre use | 2% | about US$0.3m |
| 3. Grid offer | Firm capacity and date | 5% | about US$0.7m |
| 4. Equipment order | Contracts for transformers, generators, cooling; delivery dates | 30% | about US$2.7m |
| 5. Construction | Contractor progress, cost to complete, insurance | 50% | about US$6.0m |
| 6. Energisation | Power on; commissioning; lease rent start | 10% | about US$6.7m |
What it means for the developer. Each milestone removes a risk the lender would otherwise price. The early milestones are cheap to fund and expensive to get wrong: a slip at the grid offer pushes every later step back.
Formula 1 (ICONIC): Cost of slip at milestone k = Debt drawn to k × r × months ÷ 12
Insurance matters at milestones 5 and 6. Reed Smith and Lockton discuss builder’s risk, delay in start-up cover and wrap-up policies for data centre construction (Reed Smith, 2025).
Topics to consider at this stage
- Is each milestone a condition to drawdown, or only to the next stage?
- Is delay in start-up insured, and for how long?
| Number | Why it matters |
|---|---|
| Milestones already proven | They reduce the risk priced at close |
| Long-lead equipment dates | The most common source of slip |
| Cost of a three-month slip at energisation | It sizes contingency and the interest reserve |
| Cost inflation allowance | Data centre costs rose 5.5% in 2025 |
Each milestone removes a risk the lender would otherwise price.
Key number
US$0.2m → US$6.7m
Chapter 3
What’s the bottom line?
A developer who reaches the lender with site control, a grid offer and equipment orders in hand pays for less risk, and draws faster.
Data centre construction finance is a schedule of proofs. A developer who reaches the lender with site control, a grid offer and equipment orders in hand pays for less risk, and draws faster.
For the developer, this leads to three steps:
- Prove site control and the grid offer before seeking construction debt.
- Order long-lead equipment early, and show the lender the delivery dates.
- Size contingency and the interest reserve on the cost of a late slip, not an early one.
Data centre construction finance is a schedule of proofs.
Key number
7–10%
How ICONIC can help
ICONIC Project Finance Advisory works with sponsors, owners and investors on the questions this Insight raises.
- Data centre programmes. Delivery milestones, drawdown conditions and lender reporting. Discuss your programme.
- Project finance transactions. Construction loan structuring. Pre-screen your financing.
Summary
Grid operators now test land and readiness before granting capacity (Wikborg Rein, 2026; Norton Rose Fulbright, 2026). Equipment and connections set build times (Bain, 2025), and costs rose 5.5% in 2025 with a 7–10% AI premium in the US (Turner & Townsend, 2025). In ICONIC’s worked case of a US$550m campus, a three-month slip costs about US$0.2m in interest at site control and about US$6.7m at energisation.
Frequently asked questions
What is a drawdown condition?
A requirement the borrower must meet before the lender releases each tranche of a loan.
What is delay in start-up insurance?
Cover for the revenue or debt service lost when an insured event delays completion.
References
- Bain & Company (2025) Next phase of data center growth to be more disciplined… 22 October 2025.
- Flyvbjerg, B., Holm, M.S. and Buhl, S. (2002) ‘Underestimating costs in public works projects: error or lie?’, Journal of the American Planning Association, 68(3).
- Norton Rose Fulbright (2026) Grid connections for BESS and data centers reimagined. February 2026.
- Reed Smith (2025) Key insurance concepts and issues for data center construction. Podcast transcript.
- Turner & Townsend (2025) Data centre construction cost index 2025–2026, press release.
- Turner & Townsend (2026) Surging demand for AI drives race to deliver data centres, press release.
- Wikborg Rein (2026) Option agreements in data centre development. 2026.
This Insight is for general information only and does not constitute investment, legal or tax advice.