Lenders fund a data centre one milestone at a time, from site control to energisation

Open electrical control panel

In brief

  • One campus, six milestones. Site control, zoning, grid offer, equipment order, construction and energisation. At each, the lender asks for proof that a risk has gone before it releases money.
  • The tests are getting stricter upstream. Norway’s grid operator now requires binding and exclusive access to land before granting capacity (Wikborg Rein, 2026). Germany’s transmission operators propose an 18-point maturity score (Norton Rose Fulbright, 2026).
  • A slip costs more the later it comes. In ICONIC’s worked case of a US$550m campus, a three-month slip costs about US$0.2m in interest at site control and about US$6.7m at energisation. Turner & Townsend reports 5.5% cost inflation for traditional data centres in 2025 (Turner & Townsend, 2025).

Chapter 1

What must a data centre have before the first drawdown?

In power, equipment and labour:

Site control, a path to power and a credible budget. Wikborg Rein describes option agreements as “one of the key tools” for securing land in Norway. They let developers advance zoning and grid applications while deferring the purchase (Wikborg Rein, 2026). Under Statnett’s revised maturity framework, an applicant must show binding and exclusive access to the land (Wikborg Rein, 2026). The German TSOs’ proposed scoring rates projects on land and permits, technical readiness, developer capability and system value (Norton Rose Fulbright, 2026).

Download the PDF

Where do data centre builds slip?

In power, equipment and labour:

  • Bain reports equipment lead times of 8–24 months and utility connection delays of up to five years. Four actions can cut build times by up to a year (Bain, 2025).
  • Turner & Townsend’s index of over 500 projects in 62 markets finds that demand for AI capacity has outpaced the supply of powered land and skilled labour (Turner & Townsend, 2026).
  • It also finds a 7–10% US construction cost premium for AI data centres over traditional ones (Turner & Townsend, 2025).
  • Flyvbjerg, Holm and Buhl (2002) show that cost underestimation is systematic in large projects.

Topics to consider at this stage

  • Which milestones are proven today, and which depend on third parties?
  • Which long-lead items must be ordered before the loan closes?

Site control, a path to power and a credible budget.

Key number

5.5%

Data centre cost inflation 2025. Source: Turner & Townsend.

Inside the paper

Lenders fund a data centre one milestone at a time, from site control to energisation

DOC IPFA-INS-PF-PFT-2611-IPF-050-V2

Fill out the form to read the full paper.

PDF edition

Download the full Insight

Register below. We will ask you to confirm your e-mail address and then send you a personal download link.

Chapter 2

Framework: what does the lender test at each milestone?

The framework follows one campus through six milestones.

The framework follows one campus through six milestones. The arithmetic is ICONIC’s.

MilestoneWhat the lender testsShare of spendCost of a three-month slip
1. Site controlOption or title; mortgage path3%about US$0.2m
2. ZoningPermission for data centre use2%about US$0.3m
3. Grid offerFirm capacity and date5%about US$0.7m
4. Equipment orderContracts for transformers, generators, cooling; delivery dates30%about US$2.7m
5. ConstructionContractor progress, cost to complete, insurance50%about US$6.0m
6. EnergisationPower on; commissioning; lease rent start10%about US$6.7m
Exhibit 1. One 50 MW campus, milestone by milestone. (ICONIC calculation: total cost US$550m; debt 65% of each payment; interest 7.5%; cost of a three-month slip on the debt drawn by that milestone)

What it means for the developer. Each milestone removes a risk the lender would otherwise price. The early milestones are cheap to fund and expensive to get wrong: a slip at the grid offer pushes every later step back.

Formula 1 (ICONIC): Cost of slip at milestone k = Debt drawn to k × r × months ÷ 12

Insurance matters at milestones 5 and 6. Reed Smith and Lockton discuss builder’s risk, delay in start-up cover and wrap-up policies for data centre construction (Reed Smith, 2025).

Topics to consider at this stage

  • Is each milestone a condition to drawdown, or only to the next stage?
  • Is delay in start-up insured, and for how long?
NumberWhy it matters
Milestones already provenThey reduce the risk priced at close
Long-lead equipment datesThe most common source of slip
Cost of a three-month slip at energisationIt sizes contingency and the interest reserve
Cost inflation allowanceData centre costs rose 5.5% in 2025
Exhibit 2. Four numbers before a data centre construction loan.

Each milestone removes a risk the lender would otherwise price.

Key number

US$0.2m → US$6.7m

Cost of a three-month slip, site to energisation. Source: ICONIC calculation.

Chapter 3

What’s the bottom line?

A developer who reaches the lender with site control, a grid offer and equipment orders in hand pays for less risk, and draws faster.

Data centre construction finance is a schedule of proofs. A developer who reaches the lender with site control, a grid offer and equipment orders in hand pays for less risk, and draws faster.

For the developer, this leads to three steps:

  1. Prove site control and the grid offer before seeking construction debt.
  2. Order long-lead equipment early, and show the lender the delivery dates.
  3. Size contingency and the interest reserve on the cost of a late slip, not an early one.

Data centre construction finance is a schedule of proofs.

Key number

7–10%

AI cost premium, US. Source: Turner & Townsend.

How ICONIC can help

ICONIC Project Finance Advisory works with sponsors, owners and investors on the questions this Insight raises.

  • Data centre programmes. Delivery milestones, drawdown conditions and lender reporting. Discuss your programme.
  • Project finance transactions. Construction loan structuring. Pre-screen your financing.

Summary

Grid operators now test land and readiness before granting capacity (Wikborg Rein, 2026; Norton Rose Fulbright, 2026). Equipment and connections set build times (Bain, 2025), and costs rose 5.5% in 2025 with a 7–10% AI premium in the US (Turner & Townsend, 2025). In ICONIC’s worked case of a US$550m campus, a three-month slip costs about US$0.2m in interest at site control and about US$6.7m at energisation.

Frequently asked questions

What is a drawdown condition?

A requirement the borrower must meet before the lender releases each tranche of a loan.

What is delay in start-up insurance?

Cover for the revenue or debt service lost when an insured event delays completion.

References

  • Bain & Company (2025) Next phase of data center growth to be more disciplined… 22 October 2025.
  • Flyvbjerg, B., Holm, M.S. and Buhl, S. (2002) ‘Underestimating costs in public works projects: error or lie?’, Journal of the American Planning Association, 68(3).
  • Norton Rose Fulbright (2026) Grid connections for BESS and data centers reimagined. February 2026.
  • Reed Smith (2025) Key insurance concepts and issues for data center construction. Podcast transcript.
  • Turner & Townsend (2025) Data centre construction cost index 2025–2026, press release.
  • Turner & Townsend (2026) Surging demand for AI drives race to deliver data centres, press release.
  • Wikborg Rein (2026) Option agreements in data centre development. 2026.

This Insight is for general information only and does not constitute investment, legal or tax advice.

About this article

Authors

ICONIC Infrastructure TeamInfrastructure, ICONIC Project Finance Advisory

Approved by

Georgos S. AndrianopoulosCFO & Family Office Project Finance InvestmentProfessional EUR-ING by academic training and Chartered Financial Analyst, Georgos turned a long CFO career into international project, shipping and corporate finance. A motorsport enthusiast and car aficionado, he brings the same discipline to every transaction: precise set-up, rigorous modelling and timing at financial close, across maritime, infrastructure, oil and gas, renewables and PPPs. He tunes each transaction like a race car.Georgos S. AndrianopoulosProfessional EUR-ING by academic training and Chartered Financial Analyst, Georgos turned a long CFO career into international project, shipping and corporate finance. A motorsport enthusiast and car aficionado, he brings the same discipline to every transaction: precise set-up, rigorous modelling and timing at financial close, across maritime, infrastructure, oil and gas, renewables and PPPs. He tunes each transaction like a race car.

Related insights