A hotel opens before it earns, and its construction loan has to allow for that

Building under construction, B/W

In brief

  • Before: a loan sized like an office’s. A construction loan sized only on cost and completion assumes the asset earns once it is built. A hotel does not: it fills over several years after opening.
  • After: interest due while income ramps up. In ICONIC’s worked case, a US$60m hotel opening at 40% of its stabilised profit covers its first year’s interest only at a 0.71× cover on a 60% loan, and 0.61× on a 70% loan.
  • The bridge: a loan built for the ramp-up. An interest reserve, a completion test and a conversion test on stabilised cash flow. HVS reports that lenders now lend on “in-place cash flow” (HVS, 2024); for a new hotel, there is none yet.

Chapter 1

Why is a hotel harder to fund during construction than an office?

HVS reported in 2021 that building material prices in India had risen by 30–50% in a year, and that developers were turning to prefabricated and modular methods (HVS, 2021).

An office is let before it opens; a hotel starts selling rooms on the day it opens. Its income depends on how quickly it builds occupancy and rate in its market. That takes years, not months, and the loan starts accruing interest on the first drawdown. HVS reports that the practice of benchmarking new construction costs against sales prices has given way to lending on in-place cash flow (HVS, 2024), which a hotel under construction does not have.

Download the PDF

What do rising input costs do to the budget?

They raise the equity needed and narrow the margin for error. HVS reported in 2021 that building material prices in India had risen by 30–50% in a year, and that developers were turning to prefabricated and modular methods (HVS, 2021). The Bain brief on large projects notes that 80–90% of costs are incurred in the later phases, so the decisions that set cost are made early (Bain). Flyvbjerg, Holm and Buhl (2002) show that underestimated costs are the rule in large projects, not the exception.

Topics to consider at this stage

  • How long will the hotel take to reach stabilised occupancy in its market?
  • What contingency does the budget hold, and who pays above it?

An office is let before it opens; a hotel starts selling rooms on the day it opens.

Inside the paper

A hotel opens before it earns, and its construction loan has to allow for that

DOC IPFA-INS-PF-PFT-2611-IPF-044-V2

Fill out the form to read the full paper.

PDF edition

Download the full Insight

Register below. We will ask you to confirm your e-mail address and then send you a personal download link.

Chapter 2

Step 1. Interest during construction

At an average of half the loan drawn over two years, construction interest is about US$2.9m on a 60% loan and US$3.4m on a 70% loan.

The framework follows the loan from the first drawdown to conversion. The arithmetic is ICONIC’s.

Loan-to-costLoanEquityCover year 1Cover year 2Cover year 3
60%US$36.0mUS$24.0m0.71×1.25×1.78×
70%US$42.0mUS$18.0m0.61×1.07×1.52×
Exhibit 1. The ramp-up. (ICONIC calculation: 200 rooms, total cost US$60m, 24-month build; stabilised EBITDA US$6.0m, reached in year 3 after opening at 40% and 70%; interest 8%; cover measured on a 25-year amortisation)

Formula 1 (ICONIC): Construction interest ≈ Loan × r × build years × average share drawn

At an average of half the loan drawn over two years, construction interest is about US$2.9m on a 60% loan and US$3.4m on a 70% loan.

Key number

0.71× / 0.61×

Year 1 cover at 60% / 70% LTC. Source: ICONIC calculation.

Chapter 3

Step 2. Interest during the ramp-up

In the worked case, the hotel’s EBITDA falls short of interest in year 1 by about US$0.5m on a 60% loan and US$1.0m on a 70% loan.

Formula 2 (ICONIC): Ramp-up shortfall = Σ max(0, Interest − EBITDA) over the ramp-up years

In the worked case, the hotel’s EBITDA falls short of interest in year 1 by about US$0.5m on a 60% loan and US$1.0m on a 70% loan.

Chapter 4

Step 3. Conversion

The interest reserve must cover construction and the ramp-up: about US$3.4m on a 60% loan and US$4.3m on a 70% loan in this case.

The loan converts to a term loan once the cover meets the lender’s test on actual cash flow. At a 1.30× test, both loans convert only in year 3.

What it means for the developer. The interest reserve must cover construction and the ramp-up: about US$3.4m on a 60% loan and US$4.3m on a 70% loan in this case. A higher loan-to-cost saves equity at the start and spends some of it again in the reserve.

Topics to consider at this stage

  • Is the interest reserve funded from the loan or from equity?
  • What happens if the hotel has not reached the conversion test by the loan’s maturity?

A higher loan-to-cost saves equity at the start and spends some of it again in the reserve.

Key number

about US$3.4m / US$4.3m

Interest reserve needed. Source: ICONIC calculation.

Chapter 5

Framework: what must the construction loan cover after opening?

The framework follows the loan from the first drawdown to conversion.

NumberWhy it matters
Interest during constructionIt is part of the budget
Shortfall during the ramp-upIt must be reserved
Year of conversion at the lender’s testIt sets the loan term
Cost overrun the equity can carryIt decides whether the hotel opens
Exhibit 2. Four numbers before a hotel construction loan.

Key number

Year 3

Conversion at 1.30×. Source: ICONIC calculation.

Chapter 6

What’s the bottom line?

The developer who models the ramp-up and funds the reserve for it avoids a loan that is in breach before the hotel has a chance to earn.

A hotel construction loan is sized to the year the hotel stabilises, not the day it opens. The developer who models the ramp-up and funds the reserve for it avoids a loan that is in breach before the hotel has a chance to earn.

For the developer, this leads to three steps:

  1. Model occupancy and rate year by year from opening, not a stabilised year from day one.
  2. Size the interest reserve to cover construction and the ramp-up.
  3. Agree a conversion test, and a term long enough for the hotel to reach it.

A hotel construction loan is sized to the year the hotel stabilises, not the day it opens.

How ICONIC can help

ICONIC Project Finance Advisory works with sponsors, owners and investors on the questions this Insight raises.

  • Real estate. Feasibility, ramp-up modelling and construction loan sizing. Discuss your hotel project.
  • Development finance. Lender approach, reserves and completion tests. Pre-screen your financing.

Summary

A new hotel fills over years after it opens, and lenders now lend on in-place cash flow (HVS, 2024). Input costs can rise fast (HVS, 2021), and most costs are set by early decisions (Bain). In ICONIC’s worked case, a US$60m hotel covers its first year’s interest at only 0.71× on a 60% loan. It needs an interest reserve of about US$3.4m to reach conversion in year 3.

Frequently asked questions

What is an interest reserve?

An amount set aside in the loan budget to pay interest until the project earns enough to pay it itself.

Why not borrow more to cover the ramp-up?

Because the extra debt also bears interest, and the conversion test is on actual cash flow. Borrowing more lowers the cover in every ramp-up year.

References

  • Bain & Company (n.d.) Large project management in oil and gas. Bain Brief.
  • Flyvbjerg, B., Holm, M.S. and Buhl, S. (2002) ‘Underestimating costs in public works projects: error or lie?’, Journal of the American Planning Association, 68(3).
  • HVS (2021) Monday Musings: hotel development feels the heat of rising input costs. HVS.
  • HVS (2024) Understanding the current state of the hotel transaction market. HVS.

This Insight is for general information only and does not constitute investment, legal or tax advice.

About this article

Authors

ICONIC Real Estate TeamReal Estate, ICONIC Project Finance Advisory

Approved by

Georgos S. AndrianopoulosCFO & Family Office Project Finance InvestmentProfessional EUR-ING by academic training and Chartered Financial Analyst, Georgos turned a long CFO career into international project, shipping and corporate finance. A motorsport enthusiast and car aficionado, he brings the same discipline to every transaction: precise set-up, rigorous modelling and timing at financial close, across maritime, infrastructure, oil and gas, renewables and PPPs. He tunes each transaction like a race car.Georgos S. AndrianopoulosProfessional EUR-ING by academic training and Chartered Financial Analyst, Georgos turned a long CFO career into international project, shipping and corporate finance. A motorsport enthusiast and car aficionado, he brings the same discipline to every transaction: precise set-up, rigorous modelling and timing at financial close, across maritime, infrastructure, oil and gas, renewables and PPPs. He tunes each transaction like a race car.

Related insights