ICONIC Project Finance Advisory logo ICONIC
Project Finance Advisory

In offshore wind, the CfD and the turbine contract set the debt

Wind turbines in the ocean, cloudy sky

In brief

  • Two contracts set the debt.; The revenue contract fixes the price: a contract for difference (CfD), a corporate power purchase agreement (PPA), or none; The construction contracts fix the cost and the risk of getting there: a single wrap, or several contracts.
  • The evidence: Steffen (2018) shows the central role of project finance in renewable energy, and how its use varies with technology and policy. Egli, Steffen and Schmidt (2018) show that improving financing conditions were a large part of the fall in renewable energy costs.
  • The comparison: in ICONIC’s worked case of a 1 GW farm, a CfD with a construction wrap supports about US$2.8bn of debt. The same farm on merchant revenue with several contracts supports about US$1.7bn.

Chapter 1

What does an offshore wind lender lend against?

The revenue contract decides how much of the price risk the lender must carry.

Against the farm’s revenue contract and its construction contracts. The turbines, foundations and cables are the security, but a lender cannot easily sell an offshore wind farm. Wikborg Rein notes that Norwegian law has lacked an adequate basis for security over offshore wind production assets. It calls this unsatisfactory for potential lenders (Wikborg Rein, 2021). Projects are large: Nordseecluster, owned by RWE (51%) and Norges Bank Investment Management (49%), is a 1.6 GW farm, the largest under construction off the German coast (Clarksons, 2025).

Download the PDF

Why do the revenue and turbine contracts matter most?

An offshore wind farm is two contracts and a sea. The revenue contract decides how much of the price risk the lender must carry. Norway’s Sørlige Nordsjø II tender offers capped support through a CfD (Wikborg Rein, 2023). Onshore, Bute Energy’s Twyn Hywel project raised £160m of bank debt after securing a CfD at £72.24/MWh for its full capacity (Reed Smith, 2026). The construction contracts decide who carries interface risk between turbine, foundation, cable and installation vessel.

Topics to consider at this stage

  • How much of the output is covered by the revenue contract, and for how long?
  • Is construction under one wrap, or several contracts with the sponsor managing interfaces?

An offshore wind farm is two contracts and a sea.

Key number

1.6 GW

Nordseecluster. Source: Clarksons.

Inside the paper

In offshore wind, the CfD and the turbine contract set the debt

DOC IPFA-INS-PF-PFT-2611-IPF-059-V2

Fill out the form to read the full paper.

PDF edition

Download the full Insight

Register below. We will ask you to confirm your e-mail address and then send you a personal download link.

Chapter 2

Framework: how much debt does each combination support?

The framework compares four combinations on the debt each supports.

The framework compares four combinations on the debt each supports. The arithmetic and the assumed lender terms are ICONIC’s.

Formula 1 (ICONIC): Debt = (CFADS ÷ DSCR) × annuity factor at (base rate + spread)

RevenueConstructionDSCRSpreadDebt
CfDSingle wrap1.15×160 bpabout US$2.83bn
CfDSeveral contracts1.20×190 bpabout US$2.65bn
Corporate PPASeveral contracts1.35×230 bpabout US$2.29bn
MerchantSeveral contracts1.75×300 bpabout US$1.68bn
Exhibit 1. A 1 GW offshore wind farm under four contract combinations. (ICONIC calculation: CFADS US$300m a year; 18 years; base rate 4.4%; cover ratios and spreads are ICONIC assumptions for each combination)

What it means for the sponsor. The CfD fixes the price; the turbine contract fixes the cost of getting there. On these assumptions, moving from a CfD to merchant revenue costs about US$1.1bn of debt. A wrap adds about US$180m over several contracts, which the sponsor pays for in the contractor’s price.

Topics to consider at this stage

  • What does the wrap cost, and is it worth the debt it buys?
  • What tail beyond the CfD does the lender size on?
NumberWhy it matters
Share and term of output under the revenue contractIt sets the cover ratio
Construction structureIt sets the spread and contingency
Debt under the two best combinations availableThe real choice
Cost of the wrap against its debtWhether to buy it
Exhibit 2. Four numbers before financing an offshore wind farm.

The CfD fixes the price; the turbine contract fixes the cost of getting there.

Key number

US$2.83bn / US$1.68bn

Debt with CfD and wrap / merchant. Source: ICONIC calculation.

Chapter 3

What’s the bottom line?

A sponsor who chooses the revenue and construction structure with the debt in view raises more from the same farm, or pays less for it.

Offshore wind debt is sized on the CfD and priced on the construction contracts. A sponsor who chooses the revenue and construction structure with the debt in view raises more from the same farm, or pays less for it.

For the sponsor, this leads to three steps:

  1. Size the debt under the revenue contracts available, not only the best one.
  2. Price the wrap against the debt and spread it buys.
  3. Agree the lenders’ security package early where the law is untested.

Offshore wind debt is sized on the CfD and priced on the construction contracts.

Key number

£72.24/MWh, £160m

Twyn Hywel. Source: Reed Smith.

How ICONIC can help

ICONIC Project Finance Advisory works with sponsors, owners and investors on the questions this Insight raises.

  • Renewable energy. Revenue and construction structuring for offshore wind. Discuss your project.
  • Project finance transactions. Debt sizing and lender approach. Pre-screen your financing.

Summary

Project finance is central to renewable energy, and its use varies with technology and policy (Steffen, 2018). Improving financing conditions drove much of the fall in renewable costs (Egli, Steffen and Schmidt, 2018). CfDs back offshore and onshore debt, as Sørlige Nordsjø II and Twyn Hywel show (Wikborg Rein, 2023; Reed Smith, 2026). In ICONIC’s worked case, a 1 GW farm supports about US$2.8bn with a CfD and a wrap, and about US$1.7bn on merchant revenue.

Frequently asked questions

What is a construction wrap?

A single contract under which one contractor takes responsibility for the whole project, including the interfaces between its parts.

Why does merchant revenue need a higher cover ratio?

Because the lender is exposed to the power price, and sizes on a downside price rather than a contracted one.

References

  • Clarksons (2025) Construction begins on Nordseecluster offshore wind farm warehouse at Port of Eemshaven. September 2025.
  • Egli, F., Steffen, B. and Schmidt, T.S. (2018) ‘A dynamic analysis of financing conditions for renewable energy technologies’, Nature Energy, 3(12).
  • Reed Smith (2026) Reed Smith advises Bute Energy on £160 million financing for Twyn Hywel Energy Park.
  • Steffen, B. (2018) ‘The importance of project finance for renewable energy projects’, Energy Economics, 69.
  • Wikborg Rein (2021) Debt capital financing of offshore wind projects.
  • Wikborg Rein (2023) Launch of offshore wind tenders for Sørlige Nordsjø II and Utsira Nord.

This Insight is for general information only and does not constitute investment, legal or tax advice.

About this article

Authors

ICONIC Energy TeamEnergy, ICONIC Project Finance AdvisoryPower bought from a plant not yet built is a promise in steel and cable. We test every link between the panels and the buyer before you sign: the PPA, the grid, curtailment and the financing.ICONIC Energy TeamPower bought from a plant not yet built is a promise in steel and cable. We test every link between the panels and the buyer before you sign: the PPA, the grid, curtailment and the financing.

Approved by

Georgos S. AndrianopoulosCFO & Family Office Project Finance InvestmentProfessional EUR-ING by academic training and Chartered Financial Analyst, Georgos turned a long CFO career into international project, shipping and corporate finance. A motorsport enthusiast and car aficionado, he brings the same discipline to every transaction: precise set-up, rigorous modelling and timing at financial close, across maritime, infrastructure, oil and gas, renewables and PPPs. He tunes each transaction like a race car.Georgos S. AndrianopoulosProfessional EUR-ING by academic training and Chartered Financial Analyst, Georgos turned a long CFO career into international project, shipping and corporate finance. A motorsport enthusiast and car aficionado, he brings the same discipline to every transaction: precise set-up, rigorous modelling and timing at financial close, across maritime, infrastructure, oil and gas, renewables and PPPs. He tunes each transaction like a race car.

Related insights