Every offshore wind bid sets a ceiling on the debt, whether the bidder sees it or not

Three white turbines on sea

In brief

  • The belief: winning the tender is the goal.
  • The reality: the strike price fixes the revenue, and the revenue fixes the debt. A bid below the debt the plan needs wins a project that cannot close. Egli, Steffen and Schmidt (2018) show how much financing conditions shape renewable energy costs.
  • The ceiling: in ICONIC’s worked case of a 1.5 GW farm costing £4.5bn, a strike price of £80/MWh supports debt of about 65% of cost. At £60/MWh, the figure is about 41%, and at £50/MWh about 29%.

Chapter 1

How are offshore wind sites awarded?

The sponsor must then put in more equity, renegotiate, or walk away and pay the penalty.

Increasingly by auction. Norway’s Sørlige Nordsjø II, 1,500 MW, was offered to one consortium through an English-style open-bid auction (Wikborg Rein, 2023):

Download the PDF

  • at most eight bidders were pre-qualified;
  • the winner is eligible for capped support through a contract for difference (CfD);
  • each bidder had to post an on-demand guarantee for a possible NOK 400m penalty;
  • the tender rules allow “limited possibilities to change the projects negatively after award”.

The bid is the first financing decision, taken before any lender sees the project.

What happens to projects that bid too low?

They win a CfD whose revenue cannot carry the debt the plan assumed. The sponsor must then put in more equity, renegotiate, or walk away and pay the penalty. Egli, Steffen and Schmidt (2018) show that financing conditions are a large part of the cost of renewable energy. A bid that ignores what lenders will lend against the strike price ignores a large part of its own cost.

Topics to consider at this stage

  • What gearing does the bid model assume, and at what cover ratio?
  • What penalty or guarantee is lost if the project does not proceed?

The bid is the first financing decision, taken before any lender sees the project.

Key number

about £530m

Debt lost per £10/MWh. Source: ICONIC calculation.

Inside the paper

Every offshore wind bid sets a ceiling on the debt, whether the bidder sees it or not

DOC IPFA-INS-PF-PFT-2611-IPF-061-V2

Fill out the form to read the full paper.

PDF edition

Download the full Insight

Register below. We will ask you to confirm your e-mail address and then send you a personal download link.

Chapter 2

Framework: how low can a bid go before the debt no longer closes?

The framework computes the debt each strike price supports.

The framework computes the debt each strike price supports. The arithmetic is ICONIC’s.

Formula 1 (ICONIC): Debt = [(P90 output × strike − operating costs) ÷ DSCR] × annuity factor

Strike price (£/MWh)DebtDebt as share of cost
80about £2.91bnabout 65%
70about £2.38bnabout 53%
60about £1.85bnabout 41%
55about £1.59bnabout 35%
50about £1.32bnabout 29%
Exhibit 1. Debt a 1.5 GW farm supports at each strike price. (ICONIC calculation: capital cost £4.5bn; P90 output 6.0 TWh a year; operating costs £150m a year; DSCR 1.30×; 20 years at 6%)

What it means for the bidder. Every pound off the strike price comes off the debt first. On these assumptions, each £10/MWh costs about £530m of debt, which equity must replace. A bid model that keeps gearing fixed while cutting the price is wrong twice.

Topics to consider at this stage

  • At what strike price does the equity return fall below the sponsor’s hurdle, once lost debt is replaced by equity?
  • Can the bid be indexed, or does the CfD fix it in nominal terms?
NumberWhy it matters
Debt at the bid price, on the lender’s termsThe ceiling the bid sets
Equity needed to fill the restWhether the sponsor can fund it
Strike price at which equity return meets the hurdleThe floor for the bid
Penalty if the project does not proceedThe cost of bidding too low
Exhibit 2. Four numbers before submitting a bid.

Every pound off the strike price comes off the debt first.

Key number

65% / 41% / 29%

Debt share of cost at £80 / £60 / £50. Source: ICONIC calculation.

Chapter 3

What’s the bottom line?

The bidder who sizes the debt at each strike price before bidding knows the lowest price at which it can still close, and does not win a project it cannot build.

A winning bid is one the lenders can finance. The bidder who sizes the debt at each strike price before bidding knows the lowest price at which it can still close, and does not win a project it cannot build.

For the bidder, this leads to three steps:

  1. Size the debt at each candidate strike price on lenders’ terms.
  2. Compute the equity needed and the return at each.
  3. Set the bid floor where the return meets the hurdle, and do not bid below it.

A winning bid is one the lenders can finance.

Key number

1,500 MW

Sørlige Nordsjø II. Source: Wikborg Rein.

How ICONIC can help

ICONIC Project Finance Advisory works with sponsors, owners and investors on the questions this Insight raises.

  • Renewable energy. Bid-price and debt-ceiling analysis for offshore wind auctions. Discuss your bid.
  • Project finance transactions. Lender soundings before the bid. Pre-screen your financing.

Summary

Offshore wind sites are increasingly awarded by auction, with CfD support and penalties for walking away, as in Sørlige Nordsjø II (Wikborg Rein, 2023). Financing conditions shape renewable costs (Egli, Steffen and Schmidt, 2018). In ICONIC’s worked case of a 1.5 GW farm, a strike price of £80/MWh supports debt of about 65% of cost, and £50/MWh about 29%. Each £10/MWh costs about £530m of debt.

Frequently asked questions

What is a strike price?

The price a CfD guarantees the generator per MWh; the generator is topped up when the market is lower and pays back when it is higher.

Why not raise the cover ratio’s assumption to reach the bid?

Because the lender, not the bidder, sets the cover ratio. A bid model that assumes lower cover than lenders will accept overstates the debt.

References

  • Egli, F., Steffen, B. and Schmidt, T.S. (2018) ‘A dynamic analysis of financing conditions for renewable energy technologies’, Nature Energy, 3(12).
  • Wikborg Rein (2023) Launch of offshore wind tenders for Sørlige Nordsjø II and Utsira Nord.

This Insight is for general information only and does not constitute investment, legal or tax advice.

About this article

Authors

ICONIC Energy TeamEnergy, ICONIC Project Finance AdvisoryPower bought from a plant not yet built is a promise in steel and cable. We test every link between the panels and the buyer before you sign: the PPA, the grid, curtailment and the financing.ICONIC Energy TeamPower bought from a plant not yet built is a promise in steel and cable. We test every link between the panels and the buyer before you sign: the PPA, the grid, curtailment and the financing.

Approved by

Georgos S. AndrianopoulosCFO & Family Office Project Finance InvestmentProfessional EUR-ING by academic training and Chartered Financial Analyst, Georgos turned a long CFO career into international project, shipping and corporate finance. A motorsport enthusiast and car aficionado, he brings the same discipline to every transaction: precise set-up, rigorous modelling and timing at financial close, across maritime, infrastructure, oil and gas, renewables and PPPs. He tunes each transaction like a race car.Georgos S. AndrianopoulosProfessional EUR-ING by academic training and Chartered Financial Analyst, Georgos turned a long CFO career into international project, shipping and corporate finance. A motorsport enthusiast and car aficionado, he brings the same discipline to every transaction: precise set-up, rigorous modelling and timing at financial close, across maritime, infrastructure, oil and gas, renewables and PPPs. He tunes each transaction like a race car.